Purpose and goal
To build a prototype of our hydropower plant with the market´s lowest cost (LCOE), to test the system, patent the technology and seek planning permission for a commercial facility. We have had to cancel the project bacause the principal in the project, had kidney cancer and we can´t guarantee completion of the project.
Expected results and effects
We have produced all calculations and construction drawings for the module, found a number of suitable sites to test the hydropower plant in. The expected effect, to be able to produce 45 kW has not been demonstrated since the hydroelectric plant has not been built, this due to the principal´s disease.
Planned approach and implementation
We have been working in parallel with the construction, land development and construction plans. We have not been able to realize the project because of the principal´s disease.