TMHPC100/BF
Reference number | |
Coordinator | Millfill AB |
Funding from Vinnova | SEK 200 000 |
Project duration | October 2013 - June 2014 |
Status | Completed |
Purpose and goal
Concrete curing time is today a major cost for the construction industry. Millfill AB aims to continue the development and to eventually offer a high-performance concrete with a curing time of a few days while achieving a compressive strength around 80Mpa.
Results and expected effects
Millfill AB reached the expected result with a curing time of about 18 days we reach 80Mpa from previous 28 days
Approach and implementation
Through close collaboration with consultants and subcontractors, Millfill AB have with various additives shed several concrete prisms which we have implemented compressive strength validations on. Tests have been performed on equipment approved by SP, Technical Research Institute of Sweden