TMHPC100/BF

Reference number
Coordinator Millfill AB
Funding from Vinnova SEK 200 000
Project duration October 2013 - June 2014
Status Completed

Purpose and goal

Concrete curing time is today a major cost for the construction industry. Millfill AB aims to continue the development and to eventually offer a high-performance concrete with a curing time of a few days while achieving a compressive strength around 80Mpa.

Results and expected effects

Millfill AB reached the expected result with a curing time of about 18 days we reach 80Mpa from previous 28 days

Approach and implementation

Through close collaboration with consultants and subcontractors, Millfill AB have with various additives shed several concrete prisms which we have implemented compressive strength validations on. Tests have been performed on equipment approved by SP, Technical Research Institute of Sweden

The project description has been provided by the project members themselves and the text has not been looked at by our editors.