Sustainable, circular and efficient transport solution for high-capacity goods flow
Reference number | |
Coordinator | MIKA Innovation AB |
Funding from Vinnova | SEK 900 000 |
Project duration | December 2021 - August 2022 |
Status | Completed |
Venture | Innovations for a sustainable mobility system - individual applications |
Important results from the project
The TaaS solution has been developed with a conceptual level at a high maturity level. Partners with best-in-class technology for all major components and systems has been identified and relationships/partnerships has been established. Technical experts and advisors at a high executive level on a global basis with great knowledge are connected and engaged with the company. What still remains to be finalised is the first investment round. This has been delayed due to the global uncertainty with pandemic and Ukraine.
Expected long term effects
The concept and system architecture has a readiness ready to start the demo phase. The identification of relevant use cases for the first pilot installations has started and the response from potential customers are positive. First pilot installation not agreed or decided.
Approach and implementation
The work to find key stakeholders has followed the plan although with the exception of investors that has been slowed down due to the global uncertentity with pandemic and Ukraine. We foresee a delay by 3-4 months to finalise the project in total.