Road Marking Robot part 2
Reference number | |
Coordinator | STREET SMART EQUIPMENT AB |
Funding from Vinnova | SEK 200 000 |
Project duration | March 2014 - September 2014 |
Status | Completed |
Important results from the project
We have implemented all planned changes and improvments.
Expected long term effects
Field tests on the road has been executed during september to verify the productivity. From these tests our conclusion is that we will reach the requirements of the market.
Approach and implementation
All planned Changes and improvements has been implemented. These were tested first in our lab, then in a closed area outdoors and then finally in a field test during september.