Improved resource efficiency through dynamic loading control II

Reference number
Coordinator Luleå tekniska universitet - Avdelningen för geoteknologi
Funding from Vinnova SEK 3 336 778
Project duration June 2019 - May 2022
Status Completed
Venture The strategic innovation programme for Swedish mining and metal producing industry - SIP Swedish Mining Innovation

Purpose and goal

Purpose: to improve loading and resource efficiency in Sub level caving (SLC) mines. Goal: to implement the newly developed dynamic loading control model in Giron (LKABS mine planning and equipment software) and in WOLIS (LKABs wireless online loading and information system) on selected LHDs. The developed dynamic loading control model - improves resource efficiency by reduced dilution and ore loss on a ring-by-ring basis - limits the variations of iron content in hoisted ore - assists the operators in making more informed decisions regarding the loading process.

Expected results and effects

The results from the project will facilitate a full-scale implementation of the new dynamic loading control system with graphical user interface on all LHD machines in LKABs underground mines.

Planned approach and implementation

The project was based on three work packages; WP-1, which includes project coordination and administration; WP-2, which focuses on model implementation in Giron, and WP-3, which focuses on model implementation in WOLIS on selected LHD machines.

The project description has been provided by the project members themselves and the text has not been looked at by our editors.

Last updated 8 November 2022

Reference number 2018-04606