Road Status Information (RSI) - demonstrator
Reference number | |
Coordinator | Klimator AB |
Funding from Vinnova | SEK 5 961 000 |
Project duration | February 2014 - June 2015 |
Status | Completed |
Venture | Transport Efficiency |
End-of-project report | 2013-04708sv.pdf(pdf, 827 kB) (In Swedish) |
Important results from the project
The purpose of the project was to combine existing forecasting techniques with: 1 Vehicle data 2 Geosegmenting In addition 3 Create decision support through interface. The target was to conduct studies on the wester Swedish road net during winter 2014/15 based on a Volvo Car fleet and evaluate together with Svevia. Vehicle data has been established and adaptations to climate model done. Geosegmenting (detailed study of road segment regarding shadowing, altitude etc) is performed in sweeter Sweden. Interface is developed and is available on the project homepage.
Expected long term effects
The results of the project has three main features: 1 Effect 2 Work organisation 3 Business model The effect of RSI is judged to be economically beneficial. In this phase of the project, a clear and significant cost benefit is evident. A macro level (whole of Sweden) quantification is not done in this phase. The personnel of the entrepreneur Svevia has seen significant improvements in the process of preventive action decision making. Increased security and a possibility to organizational learning are the top effects. An orientation in business model and purchase methodology is performed
Approach and implementation
The project has been run from Q1 2014 to Q2 2015. The work was split in 6 ´work packages´. Effect and business model Climate model R&D, marketing Vehicle data Interace Validation measurements Every WP has been separately reported to the project manager by a project part. The project was managed through 3 gate meetings, 3 steering committee meetings and monthly project meetings. The project has mainly followed plan and with good communication between project parts. The project has been perceived positive and forward looking by the project parties.